Construction site: Modernization of air warfare ammo for F-16 fighter planes - Poznań Krzesiny

Investor: Military Infrastructure Administration in Poznań

Implementation: IV Q 2006 - III Q 2007

Scope of works: execution of high current electrical installations, delivery and installation of LV switchgear and overhead transformer station, execution of communications installations, including: fire-fighting systems, alarm systems, telephone and radio communication systems, full monitoring system, execution of sanitary, central heating and rain installations, construction of utility and warehouse buildings, fencing and embankment, execution of road and sidewalk foundations.

Construction site: Passenger terminal at Mikołaj Kopernik airport in Wrocław

Employer: Budimex Dromex S.A.

Implementation: III Q 2007 - I Q 2008

Total area: 2000 m²

Scope of works: Power systems, including, among others: basic lighting systems, evacuation and emergency lighting systems, lightning arresters, plug in sockets, guaranteed voltage, as well as low current systems: data wiring, fire signalling system, access control system, acoustic alarming system, CCTV.

Construction site: Passenger terminal T2 at Okęcie airport in Warsaw

Employer: "Przedsiębiorstwo Państwowe Porty Lotnicze"

Implementation: I Q 2004 - I Q 2008

Area: 95,000 m2

Cubature: 790,000 m3

Scope of works: high current power services, including medium voltage distribution network (medium voltage switchboards and cabling), and low voltage distribution (transformers, low voltage cabling, indoor power supply wiring, busbar bridges, distribution busways, fire ventilation power supply, chief and secondary switchboards), 380V network, power sockets, lighting, lightning arresters, and equalizer connections.

Construction site: Upgrade of Krzesiny Air Force Base and TACAN navigation aid

Investor: Wojskowy Zarząd Infrastruktury, Poznań

Implementation: I Q 2005 - IV Q 2005

Area: 4,000 sqm

Cubature: 12,000 cbm

Scope of works: Telecommunications, including IT networks, monitoring, fire alarm, anti-burglary, telephone etc. Power supply services for TACAN system, complete with civil engineering assignment.

Construction site: Modernization of air warfare ammo for F-16 fighter planes - Poznań Krzesiny

Investor: Military Infrastructure Administration in Poznań

Implementation: IV Q 2006 - III Q 2007

Scope of works: Execution of high current electrical installations, delivery and installation of LV switchgear and overhead transformer station, execution of communications installations, including: fire-fighting systems, alarm systems, telephone and radio communication systems, full monitoring system, execution of sanitary, central heating and rain installations, construction of utility and warehouse buildings, fencing and embankment, execution of road and sidewalk foundations.

Construction site: Passenger terminal at Ławica airport in Poznań

Implementation: 3 quarters

Area overall: 106,000 sqm

Cubature: 308,000 cbm

Scope of the works: high current services at the passenger terminal including low and medium voltage switchgears manufactured by Elektromontaż System Manufacturing Plant. Outdoor lighting services complemented the assignment.

The website uses cookies

As part of our website, we use cookies to provide you with services at the highest level, including in a manner tailored to individual needs. Using the website without changing the cookie settings means that they will be stored on your end device. You can change your cookie settings at any time. More details in ours "Cookies policy".