Other
Paroc production plant in Trzemeszno
Construction site: Paroc production plant in Trzemeszno
General Contractor / Employer: Przedsiębiorstwo Usług Budowlanych Broster Marek Brodecki & Mirosław Stec Sp. j.
Implementation: III Q 2019 – I Q 2020
Scope of works: installation of high-current systems and telecommunication ducts
LM Glasfiber propeller blade factory in Goleniów
Construction: LM Glasfiber propeller blade factory in Goleniów
Investor: LM Glasfiber company
Implementation: III Q 2008 – I Q 2009
Area: 11 500 m2
Within the scope of the works, our company makes the high-current systems, including delivery and assembly of: the equipment of the transformer station (the 6-field DRAWA medium-voltage switchgear and the XEnergy low-voltage main switchgear), and delivery and assembly of sub-switchgears
and makes:
medium-voltage and low-voltage outdoor networks; area lighting; Indoor Feeder; lightning protection system; grounding system; socket installations and 3-phase power supply systems; indoor lighting installation.
as well as low-current systems, including:
structured cabling; phone cabling; fire alarm system; intrusion and access control system; gas detection.
Philip Morris cigarettes factory in Kraków
Construction site: Philip Morris Production Facility in Cracow
Investor: Philip Morris
Implementation: 1999 - 2002
Overall area: 3 500 m2
Production building cubature: 35 000 m3
Warehouse overall area: 3 500 m2
Warehouse cubature: 22 700 m3
Scope of works: 0.4 kV LV main switching station, division switchgears, UPS’s, internal power supply lines, 3-phase, lighting, earthing and compensatory connections installations, emergency power supply systems, low current (fire-fighting and control) installations.
Sanitec Sanitary-Ware Production Facility in Koło
Construction site: Enlargement of Sanitec Koło Facility
Investor: Sanitec Kolo
Employer: Budimex-Dromex S.A.
Implementation time: III Q 2006 - II Q 2007
Overall area: 30 000 m2
Scope of works:
high current installations, including: MV switchgear, 1000 and 630 kVA transformers, LV and object switchgears, cable channels and internal supply lines, lighting installation, 3-phase current and plug-in sockets installation, earthing and lightning arrester installations