Power generation

Power generation

General Contractor / Employer: RAFAKO S.A.

Implementation: II Q 2020 – III Q 2020

Scope of works: delivery, assembly and commissioning of MV and LV electric switchgear for FGD in units No. 9 and No. 10

Investor: ENEA Wytwarzanie Sp. z o.o.

Implementation: IV Q. 2019 – III Q 2020

Scope of works: Modernisation of 6 Kv Z1, WC1, WC2, P4 and 24/220V DC TPS/P4 switchgear (with design documentation)

Zamawiający: Mitsubishi Hitachi Power Systems Europe GMBH

Implementation: II Q 2020 – IV Q 2020

Scope of works: installation of electrical systems

Zamawiający: Mitsubishi Hitachi Power Systems Europe GMBH

Implementation: II Q 2020 – IV Q 2020

Scope of works: installation of electrical systems

Inwestor/Zamawiający: Veolia Energia Poznań S.A.

Implementation: II Q 2018 – I Q 2019

Scope of works: delivery and assembly of a new 6kV switchgear - section A and B – 44 bays in total

Inwestor/Zamawiający: Veolia Energia Poznań S.A.

Implementation: III Q 2016 – IV Q 2017

Scope of works: delivery and assembly of a new RKW 6kV ODRA 12 switchgear – 17 bays in total

General Contractor / Employer: RAFAKO S.A.

Implementation: I Q 2019 – III Q 2020

Scope of works: design, delivery, assembly and commissioning of the electric solutions in the “turnkey” system for the Flue Gas Desulphurisation System II for units No. 1, No. 2 and No. 3 at the Ostrołęka B Power Plant

Construction site: building the wet flue gas desulfurization system of Siekierki Heat and Power Station in Warsaw

General contractor: Rafako Boiler Factory

Implementation: IV Q 2008 – IV Q 2011

The general scope of works performed by our company: The basic and the engineering design of the power evacuation and the wet flue gas desulfurization system; electrical systems - power evacuation – performed in two stages; electrical systems for the wet flue gas desulfurization system – performed in two stages.

Construction site: Installation of electrical systems for the CFB boiler in Konin Heat and Power Station

Employer: EL PAK Sp. z o.o.

Implementation: I Q 2011 - III Q 2011

Scope of works: Installation of appliances (transformers, inverter cabinets, UPS, DC switching station), supply and installation of cable ducts, installation of cables and fire protection sealing and measurements, supply and installation of earthing devices, cable structures, as-built documentation

Construction site: Flue gas desulfurization installation in power station Ostrołęka B

Investor: Powerhouse Group – Ostrołęka S.A.

Employer: Boiler Production Facility RAFAKO

Implementation: III Q 2006 - IV Q 2007

Scope of works: Delivery and installation of 20 poles for 6 kV main Odra switchgear in Flue Gas Desulfurization Facility (produced by ZPUE Elektromontaz Poznan), 19 poles for 0.4 kV Warta switchgear (produced by ZPUE Elektromontaz Poznan).
Delivery and installation of 6 kV cable lines, 0.4 cable lines, electrical installations for flue gas desulfurization systems, general electrical installations for buildings.

Show reference

Construction site: Pątnów II Power Station 460 MW (megawatt) power electric unit

Investor: Power Station - Elektrownia Pątnów II

Employer: SNC LAVALIN Polska sp. z o.o.

Implementation: III Q 2007 - III Q 2008

Scope of works: Control and measuring equipment, automatic installation, cable routes, installation of sockets and power.

Show reference

The website uses cookies

As part of our website, we use cookies to provide you with services at the highest level, including in a manner tailored to individual needs. Using the website without changing the cookie settings means that they will be stored on your end device. You can change your cookie settings at any time. More details in ours "Cookies policy".